Pushing the underpass under the railway in Kidričevo


November 17th, 2021


At the beginning of the November, a reinforced concrete underpass structure of 1200 tonnes was successfully jacked under the railway line in Kidričevo (Talum industrial track). Construction was previously built outside the railway area and then, after the closure of line and removing the embankment, pushed into final position. We moved the underpass for 21,55m in just 8hours.



  

  
 



Ranca viaduct - another incremental launching completed


February 19th, 2021


Freyssinet Adria team successfully completed incremental launching of Ranca viaduct, with the final, 38,25 meters long pulling stage. The viaduct designed as continuous prestressed concrete structure is 206 m long and 12,3 m wide. Typical spans are 37 m long. Deck construction was executed in 11 stages of typical length of 18,5 meters.


The vertical radius of the viaduct resulted in bigger part of the bridge pointing downwards, which represented an additional challenge. The behaviour of the structure in the last launching stage confirmed the pre-calculation, which indicated the need to protect the structure against slipping in the direction of launching. Slippage in the direction of launching was successfully prevented by pre-activating the braking beam.


Together with our client, Pomgrad d.d., we performed all launching stages on a weekly basis despite winter weather conditions.


External link opens in new tab or window

External link opens in new tab or window   External link opens in new tab or window 




Successfully completed incremental launching of Bridge over Morača river in Podgorica


February 11th, 2021


With the final – 65,5 meters long launch, we successfully completed incremental launching of the 151,2 meters long and 21,8 meters wide Bridge over Morača river in Podgorica, Montenegro. In the next phase, the  31-meter-high pylon will be constructed with 7 stay cables, which will support the bridge deck.


Good job Freyssinet Adria & Freyssinet Serbia team!


External link opens in new tab or window

External link opens in new tab or window

External link opens in new tab or window

 



Prestressed slabs for first IKEA store in Slovenia


May 19th, 2020


The first IKEA store in Slovenia is being built in Ljubljana BTC City and Freyssinet Adria was there to help make it happen. At the beginning of May 2020, we successfully completed the last prestressing of the floor slabs and beams. For slabs we used F-Range 1F15 system (unbonded greased sheathed strand) and for beams C-Range system 7C15 and 12C15 (bonded steel strands in corrugated metal sheath injected with cement grout after tensioning). In total, we installed and prestressed 41 tonnes of steel strands, for post-tensioned concrete slabs on more than 10000 square meters of total area, which was divided into 10 concreting stages. Basic spans for slabs were 8x12 m and 12x12 m, higher loads were taken with prestressed beams, without additional support, which is always the tendency of the architect.


The construction was accompanied by two special circumstances: First one is the declared epidemic of COVID-19, due to which we took appropriate medical measures, to ensure that the work was carried out continuously and, to our delight, without complications. Second special circumstance was the high number of subcontractors executing the slabs, which required increased coordination and organization of work. Nevertheless, we successfully completed our part of the project in four months. 



External link opens in new tab or window  External link opens in new tab or window


External link opens in new tab or window  External link opens in new tab or window




External reinforcement of the Starše - Prepolje bridge


May 15th, 2020


In March, we successfully completed work on the Starše - Prepolje bridge over the Zlatoličje HPP supply channel. The bridge over 3 fields consists of prestressed free-standing prefabricated beams - 5 per span. The rehabilitation works included the renewal and monolithization of the superstructure and replacing the bearings. Work on the bridge was started by the main contractor RGP in 2019. During the rehabilitation - removal of damaged parts, it was found out that the prestressed cables in the prefabricated beams were more damaged, as they predicted. For this reason, the designer proposed a change in the method of reconstruction, namely additional layer of concrete on  beams and the implementation of additional external prestressing cables. Based on the designer's calculations, Freyssinet Adria prepared a proposal for the implementation of additional prestressing, execution plans and then delivered and installed all elements of external prestressed cables. Despite the unfavorable time period, the works were successfully completed.


Freyssinet Adria also supplied elastomeric bearings for the entire bridge (type BC according to EN1337 / 3 in CR version).



External link opens in new tab or windowSlika 1: Načrt deviatorja nosilcev  External link opens in new tab or windowSlika 2: Načrt tehnologije vgradnje

External link opens in new tab or windowSlika 3: Montaža nosilca deviatorjev  External link opens in new tab or windowSlika 4: Pozicionirani nosilci deviatorjev in vgrajene cevi

External link opens in new tab or windowSlika 5: Končno stanje  External link opens in new tab or windowSlika 6: Končno stanje




41st Conference of Civil Engineers of Slovenia


November 12th, 2019


The 41st Conference of Civil Engineers of Slovenia, organized by SDGK, member of the IABSE - International Association for Bridge and Structural Engineering, took place on 7 and 8 November, 2019 in Bled, Slovenia.


Again this year, Freyssinet Adria SI, d.o.o. participated with a company booth to exhibit our services and among 34 interesting professional and scientific papers, which were categorized into several thematic sections, our engineers co-authored two of them: Design and construction of the viaduct Sejanca, which presents the history of design, construction and final solution of the viaduct Sejanca on the main road G1-2 Hajdina – Ormož and Repair of structural bearings of steel bridge over the ricer Savinja in km 522+446 railway line Laško – Celje.


Take a look at some of the highlights of this year's conference.



External link opens in new tab or window   External link opens in new tab or window 

External link opens in new tab or window   External link opens in new tab or window
 



Successfully completed incremental launching of the Sejanca viaduct


September 13th, 2019


Freyssinet Adria team successfully completed incremental launching of the Sejanca viaduct at the end of August 2019 for the main contractor Pomgrad d.d.. The new viaduct represents the first section of the future highway Ormož – Ptuj, which is to be built in the coming years.

 

The 195 meters long and 12 meters wide deck crosses a double-track railway and the Sejanca brook over six spans in total. The deck was built in 11 stages with a typical length of 17,5 meters and was pulled upwards into 3,43 % incline with aid of 24 meters long launching nose. Main challenge was protecting the deck from sliding back during the ILM procedure, which was overcome by choosing suitable technology of pulling with two separate pairs of hollow jacks and two pulling beams. Approximately 4500 tons of reinforced and prestressed concrete was launched in 13 weeks in accordance with time schedule. Besides execution of ILM works, designs for concrete and steel understructure of the casting yard were also provided to the client by Freyssinet Adria construction methods department.



External link opens in new tab or window  External link opens in new tab or window


External link opens in new tab or window  External link opens in new tab or window  External link opens in new tab or window

 


The Atlantic Bridge in Panama: world record for a cable-stayed bridge

 

August 8th, 2019

 

Inaugurated on August 2, 2019, the semi-harp cable-stayed bridge called Atlantic Bridge built by VINCI Construction Grands Projets and several of its subsidiaries including Freyssinet in Panama, defies the laws of gravity and forms one of the longest cable-stayed bridges in prestressed concrete of the world.

 

With a central span of 530 meters, pylons with a height of 212.5 meters and an air draft of 75 meters, it allows the passage of the largest container ships as part of the operation of the expanded Canal and of the vehicles of the 80,000 inhabitants of the coastal communities, regardless of the operation of the locks.

 

Find out more about the project on: External link opens in new tab or windowFreyssinet


External link opens in new tab or window   External link opens in new tab or window




Prestressed floors for the new shopping center in Ljubljana


July 10th, 2019

Slovenia’s most modern shopping center, Aleja, which is being built in the Šiška district of Ljubljana, will be openned next year.

Freyssinet Adria supplied and installed 268 tonnes of HDPE steel strands for the post-tensioned concrete floors on more than 32,000 square meters of total area.
Larger distances of interior spaces and passages without support have been enriched with prestressed beams in which we have installed more than 25 tonnes of steel strands.


External link opens in new tab or window   External link opens in new tab or window   External link opens in new tab or window




Magazine - our latest edition is now available!



July 10th, 2019
 
You are welcome to have a look at the new magazine Structure to keep up with our latest news and projects!

You will discover how Freyssinet has contributed to widen the Rande Bridge in Spain, slide the new deck of the Marly-Le-Roi viaduct and many other projects.


To download the magazine, click on the image.













External link opens in new tab or window



Incremental launching of the Sejanca viaduct



May 31th, 2019

This week we successfully carried out the first phase of the incremental launching of the Sejanca viaduct, the first of many road structures to be constructed on the section of the Ptuj – Ormož connecting road.

With this construction method each segments of the bridge deck is built in workshop (formwork) placed behind abutment, in this particular case behind lower abutment. Each segment is pulled out of formwork toward final position, after being connected with previous segment via prestresed cables type Freyssinet C range. There are 11 work cycles on the Sejanca viaduct; the lengths of segments are 26 m + 4 x 35 m + 26 m, with the total structure length of 192 m.



External link opens in new tab or window


 External link opens in new tab or window   External link opens in new tab or window
 


Pedestrian and bicycle bridge over Savinja river


April 18th, 2019

 

A new pedestrian and bicycle bridge over Savinja river near Tremerje had been solemnly opened on Saturday, 13th April. 92 meters long steel truss construction crosses Savinja river in one 80 m span. Total deck width is 4,6 m. Main truss tubes are Ø406,4x25 mm. Reinforced concrete abutments are supported with 4 bored Ø100 cm piles.


Freyssinet Adria team supplied and prestressed 16 prefabicated anchors Freyssinet Freyssibar FB50 (Ø50 mm, L = 3,4 m) with which the steel structure is connected to the abutments. In addition, Freyssinet Adria also supplied and installed both Freyssinet WRB50 expansion joints (L = 3,8 m) for the bridge.



External link opens in new tab or window   External link opens in new tab or window

External link opens in new tab or window
 
External link opens in new tab or window   External link opens in new tab or window
 


Pulling the underpass under the railway in Maribor

 

April 2nd, 2019

Last week our team carried out a pull operation at Ljubljanska ulica in Maribor – a concrete slab-type of underpass was positioned under the railway by pulling method. Construction made of reinforced concrete, weighing 500 t, was previously built beside the existing railway line and then, after the closure of line and removing the embankment, pulled into final position (movement of 15,3 m) within 3 hours.


External link opens in new tab or window  External link opens in new tab or window
 


Pushing the underpass under the railway in Podklanc near Dravograd


March 29th, 2019

Over the weekend a reinforced concrete underpass structure of 950 tonnes (5.80 meters in height, 8.20 meters in width and 6.50 meters in length ) was successfully jacked under the railway line Dravograd - Prevalje. The structure was built 15m away from the railway, in the clear and then pushed into final position. Final position was reached in 29 hours from the railway line closure, while only pushing took less time.



External link opens in new tab or window  External link opens in new tab or window  External link opens in new tab or window
 
External link opens in new tab or window  External link opens in new tab or window



Bridges to Prosperity: UGANDA 2019



February 9th, 2019

Following the success of last year’s initiative, Freyssinet has joined forces with T-Ingénierie for a new  Bridges to Prosperity project, sending five volunteers from each company to lead the construction of a new footbridge in Kapkwombola, Uganda.


The new 40-metre suspended bridge built with our volunteer team will improve the everyday lives of Kurumbono community and it will provide them safe, year-round access to vital resources.


See below a photo collection from the Opening Ceremony in connection with the lastest Freyssinet's adventure accomplished in February 2018, for the construction of the Kucyaruseke Suspended Footbridge in Rwanda!



External link opens in new tab or window  External link opens in new tab or window

External link opens in new tab or window   External link opens in new tab or window   External link opens in new tab or window



40th CONFERENCE OF CIVIL ENGINEERS OF SLOVENIA



On 19 and 20 November 2018, organized by SDGK, member of IABSE – International Association for Bridge and Structural Engineering, a 40th Annual Conference of civil engineers of Slovenia took place in Bled. As every year our company Freyssinet Adria SI, d.o.o. was also present, this time in a real winter idyll.



External link opens in new tab or window   External link opens in new tab or window   External link opens in new tab or window

Our contribution this year was based on the theme: Relaxation of imposed loads and replacement of bearings on Boršt 1 viaduct. The Highway section Razdrto - Vipava is based on a very slippery ground. Thus the technical solutions of bridging structures tried to take in account such ground conditions. One of such structures, where this issue was rather distinctive, is the Viaduct Boršt 1. Here the top of the piers is widdened into a girder on which bearings are positioned allowing transversal replacement of bearings caused by unvoluntary movement of piers. Our presentation described the procedure of relaxing of involuntary forces, the problems with which our engineers were faced and presented solutions for sustainable insertion of new bearings in the structure.

Take a look at some photos of this year's event and our presentation, for which we received excellent responses.


   External link opens in new tab or window   External link opens in new tab or windowExternal link opens in new tab or window


External link opens in new tab or window   External link opens in new tab or window




In 2018 FREYSSINET turned 75



In 2018 Freyssinet celebrates its 75th anniversary! Our company Fressinet ADRIA has been a proud member of this family for more than 10 years.


External link opens in new tab or window

Over this decade, we carried out prestressing over 4,000 tons of cables in road engineering constructiona and over 2,000 tons of cables in high-rise buildings; installed and equipped numerous viaducts and bridges with expansion joints and bearings; used incremental launching method with over 3,600 m of bridges and viaducts; manufactured and delivered over a thousand meters of prestressed ground anchors etc.


External link opens in new tab or window    External link opens in new tab or window    External link opens in new tab or window

We are proud of our achievements, and we're grateful for the trust you have placed in us. We look forward to a successful working relationship in the future.

Our vision is clear, with constant technological development, remain a reliable business partner, with a professional engineering approach, for many years to come.



New Eolift - assembly system for wind towers



The Eolift lifting system was developed by Freyssinet for the assembly of wind tower made of prefabricated concrete segments. The three systems was fabricated in Italy, send to Trairi II site in Brasil and used for the construction of 36 wind towers.







PT works on Hotel Intercontinental



At the end of 2016, we successfully completed the last prestressing floor slabs at new Intercontinental Hotel in Ljubljana. Work started in June 2016 and ended in December same year. There have been 22 prestressed floor plates and two prestressed beams. We used F - range system (1F15 mono cables), and C - range system (19C15) on two beams in the ground floor slab. The total length of prestressed cables was more than 41.000 m.



External link opens in new tab or window



Projects in year 2016






Bridge over river Soča in Plave


As part of the renovation work on bridge in village Plave, replacement of the old bridge deck with a new one has been done. Freyssinet - Adria was involved in pulling deck construction, over the existing columns. Below you can see the entire course of pulling of phase 5 (total number of phases 7). Pulling was of phase 5 was executed on 20th of September 2016.






Pulling the underpass into a place near Divača



Underpass was positioned into a place by pulling method on 11th of July 2016, under the railway line between Divača and Koper at km 2.8. The total weight of the structure was approx. 2810kN. Work has been done below the temporary railway bridge without interrupting railway traffic.



External link opens in new tab or window     External link opens in new tab or window

 Before (left) and after (right) pulling



Reinforced earth Terre Armee © - lecture



On 26th and 27th January 2016 we organized a lecture - presentation in Ljubljana and Maribor of application of reinforced earth Terre Armee ©. The presentation was performed by Mr. David Brancaz representative of Terre Armee ©, which also belongs to the group SOLETANCHE Freyssinet.

We grateful for positive respond of listneners. We also thanks representatives of the companies PNZ l.l.c. and Lineal l.l.c for their hospitality.